DOTD Project on LA 1 to Start Monday July 22nd
The
The scope of work includes cold planning asphaltic concrete, removal of concrete pavement, lime treatment, in-place stabilized base course, Superpave asphaltic concrete pavement, guard rail replacement, concrete patching, and pavement marking and signage items. It is anticipated that it will take approximately (3) three months to complete the work associated with this project.
The project was awarded to the low bidder, Gilchrist Construction Co. LLC (Alexandria, LA) in the amount of $1,330,794.70.
Permit/Detour section: Local traffic will be maintained at all times but there will be periodic lane closures and minor delays associated with this work.
Safety Reminder: DOTD appreciates your patience and reminds you to please drive with caution through the construction site and be on the lookout for work crews and their equipment.