Carter
Winn Parish, purchase Carter Crossing
S.P. #H.006732.6; FEDERAL AID PROJECT #BRO-6410(502)
The Louisiana Department of Transportation and Development (DOTD) advises the public that on September 9, 2013, construction will begin on the Carter Crossing Bridges over Dugdemona River and Dugdemona River Relief in Winn Parish. This work will begin 250’ south of the Carter Crossing Bridge over the Dugdemona River and proceed 1340’ north.
The intent of this project is to remove the existing timber bridge over the Dugdemona River and replace it with a 6 span quad beam girder bridge with 24’ clear roadway, and remove the existing pipe crossing over the Dugdemona River Relief and replace it with 2 7’X7’ box culverts. The roadway will be aggregate roadway surfacing. Associated work includes ditch realignment and replacing a cross drain pipe.
The contractor will not be required to maintain thru traffic, but will be required to maintain local access to both sides of the project. The bridge will be closed 9/23/13 and will remain closed for the duration of the project.
The project was awarded to the low bidder, WL Bass Construction Inc. in the amount of $1,097,015.50. The work associate with this project should take approximately 9 months to complete.
Permit/Detour section
Thru traffic will be not maintained but access to either end of the project is available via LA 501 and LA 505.
Safety Reminder
DOTD appreciates your patience and reminds you to please drive with caution through the construction site and be on the lookout for work crews and their equipment.
Additional Information
Call (318) 561-5100 or (800) 542-3509 or 511 or visit www.511LA.org for additional information. Motorists may also monitor the LA DOTD website @ www.dotd.la.gov, the DOTD Facebook page or the LA DOTD Twitter page, @cenlatraffic for further information.
Project Contact
Mr. David Pugh, Project Engineer
District 08, Gang 258
Office # 1-318-627-5522 or 1-318-627-5457